110kV Switchyard at Doblar Hydroelectric Power Plant |
February 2025:
As part of the reconstruction and new construction of the 110 kV switchyard at the Doblar Hydroelectric Power Plant, we signed a contract with the company Kolektor Igin for the supply and execution of all auxiliary power systems within the switchyard. The scope of the auxiliary power system includes:
- AC auxiliary power distribution boards,
- Distributed AC auxiliary power distribution boards,
- 220VDC auxiliary power distribution boards,
- 110VDC auxiliary power distribution boards,
- Rectifier,
- Inverter,
- Battery banks,
- Diesel generator,
- Auxiliary power cable connections.
The works at the site will be carried out in phases, as both Doblar 1 and Doblar 2 HPPs and the 110 kV transmission system will remain in operation. The project is expected to be completed in the first quarter of next year.
|