Contract Signing for the Construction of the Banjole Wastewater Treatment Plant (WWTP) |
January 2025:
On January 31, 2025, the company Esotech, d.d. signed a contract for the implementation of the project "Design, Construction, and Trial Operation of WWTP Banjole-Bumbište." The contract includes the design, construction, and trial operation of the wastewater treatment plant with a capacity of 9,000 PE, equipped with a primary treatment stage and a new marine outfall.
The project will be executed under the FIDIC Yellow Book model.
This initiative is part of a broader EU-funded project covering the agglomeration of Medulin, Premantura, and Banjole. The total expected project duration is 27 months, encompassing design, permit acquisition, construction, and trial operation.
This significant infrastructure project will enhance wastewater treatment quality and contribute to improved environmental protection in the Municipality of Medulin.
|