Reconstruction of the Alagovac drinking water treatment plant in the municipality of Nevesinje |
June 2022:
In accordance with the contractual requirements, the activities on the WTP Alagovac Nevesinje project have been completed to the extent that the plant is in operational condition and allows the distribution of up to 66 l / s of purified drinking water in the water supply system of Nevesinje.
The contractual scope of works included:
- a snapshot of the situation on the building (actual state) with the preparation of the Preliminary Design
- preparation of project documentation for obtaining a building permit
- preparation of PZI (main) project (for execution of works)
- supply of new technological equipment and refurbishment of existing equipment that was not in function
- execution of construction works
- execution of mechanical installation works
- execution of electrical installation works
- commissioning of the plant, training of the client's staff and implementation of trial operation with warranty measurements
The project is of great importance for the Municipality of Nevesinje in terms of ensuring a comprehensive supply of drinking water to the population of the Municipality of Nevesinje, which meets the required criteria for drinking water quality in accordance with regulations and legislation in this area and EU requirements. As part of the celebration of the Nevesinje Municipality on 2nd June 2022, in the presence of representatives of the Nevesinje Municipality, the Government of the Republika Srpska, the Ambassador of the Republic of Slovenia to BiH, CMSR representatives and other invited guests from the region, the plant was ceremoniously handed over into operation.
We would like to thank everyone for their trust, constructive cooperation in the implementation of the project and expressed kind words at the opening of the plant.
|