Reconstruction of the municipal wastewater treatment plant in the Municipality of Turnišče |
May 2022:
On 11 May 2022, Esotech, d.d., signed a contract with the client Municipality Turnišče for the reconstruction of the municipal wastewater treatment plant in Turnišče, which treats wastewater from the settlements of Turnišče, Renkovci, Gomilica and Nedelica.
The new treatment plant will be based on the MBBR method, which means that modern technology of mechanical-biological treatment of municipal wastewater with biomass carriers will be used. With the improved quality of municipal water treatment and increased capacity to 6,000 population units, the plant will significantly contribute to the sustainable development of the Municipality of Turnišče.
The contract works will be carried out in accordance with the schedule, namely the completion of the works is planned within one year from the commissioning and trial operation one year after the completion of the works.
|