Construction of a municipal wastewater treatment plant in Primošten |
January 2021:
On January 8, 2021, we signed a contract with the client Primošten Odvodnja d.o.o., Primošten for the construction of a municipal wastewater treatment plant in Primošten. Wastewater treatment plant with a capacity of 18.750 PU, includes a sewerage network and a submarine outfall. The project valued in the amount of HRK 21.6 million will be implemented within 15 months from commencement of works. The works will also take place during the tourist season.
This project is Esotech's third reference project recently in the Republic of Croatia, in the field of construction of municipal wastewater treatment plants, including a mechanical stage of wastewater treatment.
|