Execution works on blocks 6 and 5 in TE Šoštanj |
July 2018:
This year, the first regular works of 600 MW block 6 took place in Šoštanj Thermal Power Plant in the period from 7.5.2018 to 30.6.2018. In addition to the works of Block 6, works on 345 MW block 5 are also taking place and will be completed by the end of July.
The Esotech assembly team is still actively involved in the implementation of the works on blocks 6 and 5. With the preparations for the implementation of this year's repair, we started in February. The purpose was to provide qualified personnel for the execution of works on demanding energy facilities such as a thermal power plant in Šoštanj.
All works on block 6, which were within the contractual scope of Esotech, were completed within the deadline with quality and were handed over to the client. Repair works on block 5 are carried out in accordance with the time schedule. The completion of all activities is planned at the end of July.
Due to the large number of works and short deadlines for implementation, works were also carried out in some areas with an extended working day. In addition to quality implementation a lot of attention has been paid to the safe execution of works.
|