Contract for the reconstruction of drinking water treatment plant |
May 2018: On May 16th, we signed a contract with the Municipality of Nevesinje for the implementation of the project: Reconstruction of an existing plant for the preparation of drinking water. The project is technologically demanding, as it will be necessary to provide the customers with a smooth supply of drinking water throughout the reconstruction process. The contractual scope of the work covers: - design,
- procurement of technological equipment,
- execution of assembly works (construction, machine and electrical),
- start up the device,
- training the client and handing over the facility.
The deadline for the implementation is 10 months from the commencement of the work.
|