Silver national award for an innovative project »Waste Water Treatment System in the Nikola Tesla A Thermoelectric Power Plant, Obrenovac«
Technical inspection at the Slovenj Gradec RTP
March 2017:
On Wednesday, 8.3.2017, the last Technical Review in the Slovenj Gradec RTP was successfully completed: the replacement of VN of current TR and secondary connections in the 110 kV transmission line Velenje I.
Electrical installation works at the distribution transformation stations: RTP Vuzenica, RTP Slovenj Gradec - 110 kV DV field Dravograd 1, RTP Rogaška Slatina and RTP Brezice were completed until 23 January 2017, while electrical installation work in the DV field Velenje 1 - RTP SG on The proposal of the contracting authority was postponed to February 2017. The reason for the delay was the unfavorable conditions for the implementation of outdoor electrical installations, in particular very low temperatures in which control signal cables are not allowed to be laid.
The electrical installation works had to be carried out exactly in accordance with the plan of switching off the individual fields in each distribution station. The disconnection plans of individual DVs were considerably changed and deviated from the original timetable, taking into account other maintenance work and the need for shutdowns in each region.
With successfully implemented STPs of all individual phases on all RTPs, all contractual obligations have been successfully implemented.
Esotech, Joint stock company Company for Development and Implementation of Environmental Solutions and Power Technologies
Preloška cesta 1 3320 Velenje Slovenia EU
Telephone: +386 3 8994 500 Telefax: +386 3 8994 503 E-mail:
This e-mail address is being protected from spam bots, you need JavaScript enabled to view it
VAT: 73789933 more...