Central wastewater treatment plant Mozirje |
November 2016:
Finishing work on the construction of the new building mechanical treatment is being carried out and is in the final stage. Upgrading existing tanks according to a new technological concept to ensure flood safety have been completed. Rehabilitation of concrete surfaces are being carried out on the reconstructed pools: anaerobic and aerobic reactor 1, balancing pool, aerobic reactor 2 and the plate sedimentation tank. All technological equipment is delivered and in preparation for the start of assembly on site. Electrical switchboards are already under construction in our electrical workshop and will soon be ready for installation on the site. Approval for the amendment of the building permit are gained.
|