Upgrading and reconstruction of the wastewater treatment plant Jesenice |
April 2015:
We signed a contract for the upgrade and reconstruction of the central waste water treatment plant with municipality Jesenice.
Works at the site are currently at full intensity. The main construction phase of execution building was completed in February, in March we began construction work in the area of aeration basins, which are currently in the final stage. At the same time installation of equipment is performed and at the beginning of May we began with the rehabilitation work in the area of the inlet pumping station. In a short while we will start the execution of electro field.
Reconstructed central wastewater treatment plant Jesenice will be implemented as a single-stage revival device further treatment of sewage for the final building size of 30,000 PE, with the following objectives cleaning up: decomposition of organic carbon, nitrification, denitrification and phosphorus removal. |